Resource-constrained project scheduling

AbbreviationInstances of resource-constrained project scheduling#✓fully proved

An instance of resource-constrained project scheduling (an RCPSP instance) is a quadruple \((J, P, C, D)\): a list \(J\) of jobs, each a pair \((p, r) \in \mathbb{N} \times \mathbb{N}\) of a duration \(p\) and a resource demand \(r\); a list \(P\) of precedence pairs \((a, b) \in \mathbb{N} \times \mathbb{N}\) of job indices; a resource capacity \(C \in \mathbb{N}\); and a deadline \(D \in \mathbb{N}\).

abbrev RCPSPInstance := List (ℕ × ℕ) × List (ℕ × ℕ) × ℕ × ℕ
Used by 3

DefinitionWell-formed RCPSP instances#✓fully proved

An RCPSP instance \((J, P, C, D)\) whose job list \(J\) has \(n\) jobs is well formed when every precedence pair \((a, b) \in P\) satisfies \(a < n\), \(b < n\) and \(a \ne b\), and there is a listing of \(0, 1, \dots, n-1\), each exactly once, in which \(a\) comes before \(b\) for every \((a, b) \in P\).

def WellFormed (i : RCPSPInstance) : Prop :=
  ∀ p ∈ i.2.1, p.1 < i.1.length ∧ p.2 < i.1.length ∧ p.1 ≠ p.2 ∧
    ∃ ord : List ℕ, ord.Perm (List.range i.1.length) ∧
      ∀ p ∈ i.2.1, ord.idxOf p.1 < ord.idxOf p.2
Uses 1 · Used by 1

DefinitionFeasible RCPSP instances#✓fully proved

Let \((J, P, C, D)\) be an RCPSP instance with \(n\) jobs, where job \(j < n\) has duration \(p_j\) and resource demand \(r_j\), and set \(p_j = 0\) for \(j \ge n\). The instance is feasible when there are start times \(s_0, \dots, s_{n-1} \in \mathbb{N}\), with \(s_j = 0\) for \(j \ge n\), such that every job finishes by the deadline (\(s_j + p_j \le D\) for all \(j < n\)), every precedence pair \((a, b) \in P\) satisfies \(s_a + p_a \le s_b\), and at every time \(t < D\) the total demand of the jobs active at \(t\) (the jobs \(j < n\) with \(s_j \le t < s_j + p_j\)) is at most \(C\).

def RCPSPFeasible
    (i : RCPSPInstance) : Prop :=
  ∃ start : List ℕ, start.length = i.1.length ∧
    (∀ j < i.1.length, start.getD j 0 + (i.1.getD j (0, 0)).1 ≤ i.2.2.2) ∧
    (∀ p ∈ i.2.1, start.getD p.1 0 + (i.1.getD p.1 0).1 ≤ start.getD p.2 0) ∧
    ∀ t < i.2.2.2, ¬ ∃ active : List ℕ, active.Nodup ∧
      (∀ j ∈ active, j < i.1.length ∧ start.getD j 0 ≤ t ∧
        t < start.getD j 0 + (i.1.getD j (0, 0)).1) ∧
      i.2.2.1 < (active.map (fun j => (i.1.getD j (0, 0)).2)).sum
Uses 1 · Used by 1

DefinitionResource-constrained project scheduling as a decision problem#✓fully proved

RESOURCE-CONSTRAINED PROJECT SCHEDULING is the decision problem that accepts a bitstring \(x\) exactly when \(x\) decodes, under the canonical bitstring encoding of RCPSP instances, to an RCPSP instance that is well formed and feasible. Bitstrings that do not decode to an instance are rejected.

noncomputable def rcpspDec :
    MetaMathlibExt.ComplexityTheory.DecisionProblem := fun x =>
  match MetaMathlibExt.BitstringEncoding.bitDecode
      (α := RCPSPInstance) x with
  | some i => decide (WellFormed i ∧ RCPSPFeasible i)
  | none => false
Uses 12 · Used by 1

TheoremRESOURCE-CONSTRAINED PROJECT SCHEDULING is NP-complete#●ready to prove

The decision problem RESOURCE-CONSTRAINED PROJECT SCHEDULING belongs to NP, and every decision problem in NP has a polynomial-time many-one reduction to it.

public theorem_wanted rcpsp_npComplete :
    rcpspDec ∈ MetaMathlibExt.ComplexityTheory.NP ∧
      ∀ L : MetaMathlibExt.ComplexityTheory.DecisionProblem,
        L ∈ MetaMathlibExt.ComplexityTheory.NP →
          Cslib.CookLevin.PolyManyOneRed L rcpspDec
Sources
  • M. R. Garey and D. S. Johnson, Computers and Intractability (1979), BIN PACKING; J. Blazewicz, J. K. Lenstra, and A. H. G. Rinnooy Kan, "Scheduling subject to resource constraints: classification and complexity", Discrete Applied Mathematics 5 (1983), 11-24 (classification).